Inzonex
Proposal · 2026-05-27 · INZ-CLEAN-SLG-2026-001
CLEAN Linen Services · Slough Plant

£86,291 saved per year. £64,680 to install. 9.0 months payback.

Inzonex Modular Insulation across the boiler house, feed water, hot water, ironers and dryer burner cabinets. 95 % heat-loss reduction. Removable, serviceable, engineered to each element.

£86,291
Saved per year
9.0 mo
Payback
1,878 MWh
Heat saved / year
404 t
CO₂ saved / year
01 · Plant Context

CLEAN Linen Services — Slough plant.

Site visit on 25 May 2026 identified 255 m² of bare hot surface across six areas of the laundry — boiler house, feed water lines, hot-water distribution, flatwork ironers and gas-fired tumbler dryer burner cabinets. All addressable with removable Inzonex modules without modifying pipework, pumps or burners.

Steam generation

2 × Byworth Y2SZ3500-24 3-pass wetback firetube boilers (July 2016). 3,500 kg/h F&A 100 °C each. Design 10/13 BARG, saturated steam up to +190 °C. Both boilers in service — alternating weekly: 26 weeks production + 26 weeks hot standby per boiler per year. Steam feeds ironers, hot-water service and process heating.

Drying & finishing

5 flatwork ironers (4 large + 1 small) — steam-heated chests, top cabinet surface 66 °C measured. 14 Kannegiesser tumbler dryers — direct gas-fired (independent of the steam boilers), with burner + heat-exchanger cabinets on top of each drum. Surface temperature per face: front 84 °C / sides 100 °C / top ~115 °C / back 120 °C, measured on FLIR.

02 · Engineering Basis

ISO 12241 · measured T_s · honest range, not best-case.

Heat loss is computed per ISO 12241:2008 using the surface temperature actually measured by FLIR (or stated by the client). Convective coefficient at 0.5 m/s indoor draft, radiative coefficient for painted/oxidised steel (ε = 0.85), ambient 30 °C. Outer surface temperatures land between 37 °C and 45 °C — well below the UK HSE 60 °C touch limit.

Insulation system

Inzonex Modular Insulation, 50 mm mineral-wool core (λ = 0.045 W/m·K at 100 °C mean), outer surface temperature 37–45 °C, fully removable, snap-fit + lacing closures, silicone-coated outer.

Heat-flux band used

Bare: 590 – 2,340 W/m² depending on T_s (66 – 150 °C). Covered with 50 mm: 30 – 101 W/m². Average reduction across all surfaces: 95.0 %.

Pricing & savings basis

Steam cost (client-supplied): £31.28 / tonne generated by gas ≈ £45.94 / MWh thermal. Plant operating profile (all sections): 22 h/day × 4 mo + 20 h/day × 6 mo + 17 h/day × 2 mo = 7,340 h/yr. Boilers rotate weekly — one always on hot standby. CO₂ factor: 0.18293 kg/kWh gas.

03 · Scope by Area

Six discrete zones. Each one stands alone on payback.

The project can be delivered in phases — start with any single zone or commit to the full scope. Pricing, lead time and on-site work plan agreed per phase.

Feed Water pumps
Section A · 7,340 h/yr
Feed Water — 4 pump lines

DN50 isolation valves, vertical multistage pump bodies (Ø300 × 1050 mm), Y-strainers, DN40 ball valves, DN50 bends, DN150 flanges, riser flanges. Medium 102 °C, shared between both boilers.

6.5 m²
Area
7.8 kW
Saved
£2,621
£/yr
12.3 t
CO₂/yr
Both Byworth boilers in boiler house
Section B + C · rotated weekly · 7,340 h/yr/boiler
Both Boilers — Byworth Y2SZ3500 × 2

Rotated weekly — one always on hot standby. Per boiler: ~3,670 h production (28.1 kW saved) + ~3,670 h hot standby at 70 °C (11.1 kW saved). 11 element types per boiler — front door, burner flange, economizer inlet line + gas chamber, handhole, supports, rear assemblies, top valves.

37.2 m²
Area
19.6 kW
avg/boiler
£13,227
£/yr
62.0 t
CO₂/yr
Hot water PRV + ball valves
Section D · 7,340 h/yr
Hot-water distribution

Pneumatic PRV DN50, ABB flowmeter body (head excluded — T-limit), two flanged ball valves Ø111 × L220. 90 °C process line.

0.65 m²
Area
0.64 kW
Saved
£216
£/yr
1.01 t
CO₂/yr
Ironer top cabinet
Section E · 7,340 h/yr
Flatwork ironers — 5 machines

4 large multi-roll + 1 smaller (~20 % less area). Top cabinet surface 66 °C measured. Roof made almost entirely of lift-off panels — each panel jacketed individually, lifts together with the panel for maintenance access.

139 m²
Area
78.0 kW
Saved
£26,284
£/yr
123 t
CO₂/yr
Kannegiesser dryer burner cabinet
Section F · 7,340 h/yr · LARGEST PRIZE
Dryer burner+HX modules — 14 units

Kannegiesser gas-fired tumbler dryers, top-mounted burner + heat-exchanger cabinets. Surface temperature per face: front 84 °C, back 120 °C, sides 100 °C, top ~115 °C. Roughness ×1.40 for bolts, sight-glass frames, dampers, brackets, flue stubs. Single largest saving — 51 % of total annual benefit.

103 m²
Area
130 kW
Saved
£43,943
£/yr
206 t
CO₂/yr
04 · Site Evidence

Measured, not modelled.

All surface temperatures below were taken on site with FLIR. 69 thermograms recorded across the plant. Top hotspot: 167 °C. Median peak: 101 °C. 51 of 69 frames showed at least one surface above 80 °C.

126 °C
Economizer chamber visible
IMG_9481
Economizer FLIR
FLIR — 125.7 °C

Economizer flue-gas inlet chamber

Bolted steel casing carrying boiler exhaust to the finned economizer above. Single largest bare element on each boiler.

82 °C
Dryer cabinet visible
IMG_9553
Dryer FLIR
FLIR — 81.9 °C

Kannegiesser dryer — burner+HX cabinet

14 of these sit bare on top of the gas-fired tumblers. Surface temperature per face: front 84 °C, sides 100 °C, top ~115 °C, back 120 °C. Largest single saving — £43,943 / year.

140 °C
Boiler handhole
IMG_9474
Handhole FLIR
FLIR — 140.4 °C

Boiler — side handhole Ø600 mm

Bolted bridge-bar inspection cover with raised flange ring. 0.73 m² module removes 1.4 kW continuous loss.

138 °C
Boiler front
IMG_9460
Front FLIR
FLIR — 137.7 °C

Boiler — front door + burner flange

Front face 2.0 × 0.8 m with 10 cm flange perimeter, perimeter bolts, lifting eye and burner mounting flange. 3.83 m² — single largest face on each boiler.

90 °C
Feed water valves
IMG_9425
Feed water FLIR
FLIR — 90.3 °C

Feed water — bare valves at pump inlets

Header pipework above the pumps is already insulated. Every isolation valve, strainer, ball valve and pump body sits exposed.

Full thermogram set (69 shots, calibrated, with min/max/avg temperature overlay) and raw FLIR RJPEGs available on request. Pre-quote site visit will add per-face survey of every dryer cabinet and ironer roof for fabrication-grade dimensions.

05 · Detailed Heat-Loss Schedule

Every element, every surface temperature, every watt.

Full bottom-up build by section. Bare and covered heat flux per element. Annual £/yr at £31.28 / tonne of steam (≈ £45.94 / MWh thermal) × 7,340 h/yr plant operating profile (22 h/day × 4 mo + 20 h/day × 6 mo + 17 h/day × 2 mo). Boilers rotate weekly — one always on hot standby.

Section / Element T_s °C Q_bare kW Q_cov kW Saved kW £/yr
A · FEED WATER — 4 lines · 102 °C · 7,340 h/yr
Gate valves DN50 L250 × 40.721020.910.040.86290
Pump body Ø300 × 1050 × 44.001025.040.244.801,618
Y-strainers × 40.641020.810.040.77260
Ball valves DN40 × 40.481020.600.030.58195
90° bends DN50 × 40.251020.310.020.30101
Flanges DN150 × 40.191020.240.010.2376
Riser flanges DN50 × 20.201020.250.010.2481
Section A subtotal6.488.170.407.772,621
B + C · BOTH BOILERS — Byworth Y2SZ3500 × 2 · rotated weekly (one always firing, one in hot standby) · 3,670 h prod + 3,670 h standby per boiler
Production state — element-by-element, per boiler (£/yr column shown for both boilers combined = per-boiler × 2)
Front smokebox door2.651053.500.173.331,123
Burner flange1.181332.280.102.18735
Economizer inlet line (DN25 flange + DN40 pipes + 4 valves + pneumatic regulator)1.15971.340.061.28432
Side handhole Ø600 mm0.731401.530.071.47495
Boiler saddle supports × 24.40874.260.214.051,366
Economizer gas-inlet chamber5.001258.770.408.372,821
Rear access door + canopy1.581202.600.122.48836
Rear smokebox door Ø750 mm1.03951.160.061.11374
Sensor flanges DN65 × 4 (top)0.601501.400.061.34452
Safety valve 100/650.411500.960.040.92310
Main DN150 steam stop valve0.721501.690.071.61543
Production sub (per boiler × 2 = both boilers, 3,670 h each)19.4529.491.3628.149,487
Standby state — all elements uniform at 70 °C (top assembly cold-isolated)
Boiler envelope minus top assembly · per boiler × 2 boilers (3,670 h standby each)17.727011.700.6011.093,740
Section B+C subtotal (both boilers, full year)37.1713,227
D · HOT WATER · 90 °C · 7,340 h/yr
Pneumatic PRV DN500.25900.260.010.2583
Flowmeter DN40 (body only)0.12900.120.010.1240
Ball valves Ø111 × L220 × 20.28900.290.010.2893
Section D subtotal0.650.670.030.64216
E · FLATWORK IRONERS — 5 machines · 66 °C · 7,340 h/yr (full roof = lift-off panels jacketed individually)
Ironer #1 (large)29.006617.110.8716.245,476
Ironer #2 (large)29.006617.110.8716.245,476
Ironer #3 (large)29.006617.110.8716.245,476
Ironer #4 (large)29.006617.110.8716.245,476
Ironer #5 (small, −20 %)23.206613.690.7012.994,380
Section E subtotal139.2082.134.1877.9526,284
F · DRYER BURNER+HX MODULES — 14 units (Kannegiesser, ×1.40 roughness) · 7,340 h/yr
Front faces (× 14, 84 °C)31.908429.281.4427.859,391
Back faces (× 14, 120 °C)31.9012052.412.4249.9916,856
Top faces (× 14, ~115 °C est.)22.1011534.011.5932.4210,932
Side faces (× 14 net, 100 °C)17.2010021.071.0120.066,764
Section F subtotal103.10136.786.46130.3243,943
GRAND TOTAL · all sections (50 mm jacket)286.60£86,291

Q_bare and Q_cov are continuous heat fluxes (steady-state) — covered values quoted at 50 mm Inzonex Modular Insulation jacket. £/yr is the steam-cost equivalent at £31.28/tonne (≈ £45.94/MWh thermal) applied across each section's 7,340 h/yr operating profile. Total heat saved: 1,878 MWh thermal/yr ≈ 2,758 tonnes of steam.

06 · Investment & Payback

Three ways in. All under 12 months.

Each phase pays for itself, and combinations compound. Final pricing below — manufactured in Ukraine, delivered to UK, installed on site. Lead time 4–6 weeks after full on-site measurements.

Boilers + Feed Water + DHW

11.3 mo
Insulated area44.3 m²
Annual saving£16,061
CO₂ saved/yr75.3 t
Insulation£15,180

Section E — Ironers (5)

5.9 mo
Insulated area139.2 m²
Annual saving£26,284
CO₂ saved/yr123.2 t
Insulation£13,000

Section F — Dryers (14)

7.9 mo
Insulated area103.1 m²
Annual saving£43,943
CO₂ saved/yr205.9 t
Insulation£29,000

Manufactured by contractor in Ukraine to GB2508992.1. Lead time 4–6 weeks from completion of full on-site measurements. Delivered DDP — all duties, taxes and broker services included in price. Installation 1–2 days per zone; dryer cabinets installed during scheduled shutdown window. Final price subject to confirmed access, paint condition, asbestos check and finalised face-by-face FLIR survey on dryer cabinets and ironer roofs.

07 · The Solution

Inzonex Modular Removable System.

Four-layer construction. Outer silicone-coated fabric (flame-retardant, oil and chemical resistant, washable). Aluminium foil radiation barrier. Mineral-wool core, density and thickness tuned per element. Inner silicone liner against the hot face. Closed with AISI 316 stainless snap fasteners and meta-aramid thread — no exposed steel wire to wear out.

Inzonex Modular Insulation — 4-layer construction
Snap-fit access
Tool-free removal in seconds. Re-installed in seconds. 6× faster than traditional blankets.
Replaceable core
Outer shell stays. Inner insulation replaced through zipper. Service life 15+ years.
🛡
Patent protected
UK Patent GB2508992.1. Unique modular architecture with structural outer shell.
3-year warranty
Structural integrity + fastening system. Expected effective service life 12–15 years.

Materials & compliance

  • Outer layer: Silicone-coated fibreglass, flame-retardant (EN 13501-1), UV protected, oil and chemical resistant, washable. Standard grey, optional black or orange.
  • Radiation barrier: Aluminium foil 30 μm — reduces radiative loss from the hot face by ~40 %.
  • Insulation core: Industrial mineral wool 50–80 kg/m³, λ ≈ 0.045 W/m·K at 100 °C mean, up to +600 °C. 50 mm standard for this scope.
  • Inner liner: Silicone-coated fabric facing the hot surface, prevents core fibre release into the working space.
  • Fasteners: AISI 316 stainless steel snap buttons (marine grade) + meta-aramid sewing thread up to +220 °C.
  • Compliance: EN 13501-1, REACH and RoHS compliant. Asbestos-free. Recyclable mineral core.

Installation & delivery

  • Manufacture: Contractor in Ukraine. 4–6 weeks from completion of on-site measurements.
  • Delivery: DDP terms — all duties, taxes and broker services included in price (0 % additional cost to client).
  • Installation: 1–2 days per zone for boilers, feed water, hot water and ironers. Dryer cabinets installed during scheduled shutdown window only (no production interruption required for the rest).
  • Verification: Post-install FLIR thermal report. Documents outer surface temperature on every element (target 37–45 °C, below UK HSE 60 °C touch limit).
  • ESG report: Annual energy and CO₂ savings statement for sustainability reporting.
08 · Next Steps

From this proposal to fitted insulation in 8 weeks.

1
Pre-quote site visit
Full FLIR thermal survey of dryer cabinets (per-face), confirm ironer dims and counts, asbestos check. Free of charge. Week 1.
2
Firm quote + drawings
Fixed price per zone, fabrication drawings, lead-times. Phase recommendation. Week 2.
3
Manufacture
Inzonex Modular Insulation manufactured to each element's exact geometry. Weeks 3–6.
4
Fit on site
1–2 days per zone for boilers, FW, hot water, ironers — no production stop. Dryer cabinets fitted during scheduled shutdown window. Hand-over with post-fit FLIR validation.